La Loma Bridge Closure

  • La Loma Bridge News

    A June 2017 completion date is now expected for the La Loma Bridge project according to a staff report to be submitted at the February 27th City Council meeting. The project was originally expected to be completed by the end of December 2016. Unfortunately, the project has experienced unanticipated construction related delays which have…

  • La Loma Bridge Update

    La Loma Bridge Update

    According to Pasadena City Engineer Brent Maue, PE. who provided the following: The bridge is still on schedule to re-open in December 2016. The bridge demolition work is complete and the contractor has transitioned to the construction of the new sub-structure components.  As nearby residents are probably well aware, the contractor has recently been installing driven…