La Loma Bridge News
26 Feb
A June 2017 completion date is now expected for the La Loma Bridge project according to a staff report to be submitted at the February 27th City Council meeting. The project was originally expected to be completed by the end of December 2016. Unfortunately, the project has experienced unanticipated construction related delays which have pushed back the completion date. The contractor, Vali Cooper & Associates is requesting additional funds in the amount of $150,000 for construction management services through completion of the project. Almost 89% of the funds needed for the project are Federal funds. The new cost of the management services contract will be $1,250,00.00